California State Department of Transportation

Project Development Workflow Tasks (PDWT)

Project Development Workflow Tasks (PDWT)

Index

| A | B | C | D | E | G | I | M | O | P | R | S |


---------------------------------------- A ----------------------------------------

Advertise Contract (Milestone 480)

Approve Contract (Milestone 500)

Approve Draft Project Report (Milestone 100)

Approve final Environmental Document (Milestone 160)

Approve Initiation of PS&E (Milestone 200)

Approve Project Study Report (Milestone 010)

 

---------------------------------------- B ----------------------------------------

Begin Project Studies (Milestone 000)

Bridge Site Data, Send to Structures Design (Milestone 221)

 

---------------------------------------- C ----------------------------------------

Circulate Draft Environmental Document (Milestone 120)

Circulate Draft Project Report and Draft Environmental Document in District (Milestone 060)

Circulate Plans for Review (Milestone 300)

Complete Construction Project (Milestone 600)

Complete Environmental Reevaluation (Milestone 360)

Complete Geometric Base Maps (Milestone 220)

Complete PS&E and send to District Office Engineer (Milestone 377*)

Complete Special Provisions (Milestone 420*)

Conduct Public Hearing (Milestone 140)

Construction Project, Complete (Milestone 600)

Contract, Advertise (Milestone 480)

Contract, Approve (Milestone 500)

Contract, Determine is Ready to List for Advertising (Milestone 460)

 

---------------------------------------- D----------------------------------------

Determine Contract is Ready to List for Advertising (Milestone 460)

Distribute Skeleton Layouts to Functional Units (Milestone 260)

 

---------------------------------------- E ----------------------------------------

Environmental Document, Approve final (Milestone 160)

Environmental Document, Circulate Draft (Milestone 120)

Environmental Document, Circulate Draft in District (Milestone 060)

Environmental Document, Initiate Draft (Milestone 040)

Environmental Reevaluation, Complete (Milestone 360)

Environmental Studies, Initiate (Milestone 020)

 

---------------------------------------- G ----------------------------------------

Geometric Base Maps, Complete (Milestone 220)

 

---------------------------------------- I ----------------------------------------

Identify Project Need and Begin Project Studies (Milestone 000)

Initiate Draft Project Report and Draft Environmental Document (Milestone 040)

Initiate Environmental Studies (Milestone 020)

Initiate Right of Way Appraisals (Milestone 225)

Initiate Structures Design (Milestone 222)

 

---------------------------------------- M ----------------------------------------

Maps, Send Final to Right of Way (Milestone 265)

Maps, Send to Right of Way Engineering (Milestone 224)

Milestone 000 - Identify Project Need and Begin Project Studies

Milestone 010 - Approve Project Study Report

Milestone 020 - Initiate Environmental Studies

Milestone 040 - Initiate Draft Project Report and Draft Environmental Document

Milestone 060 - Circulate Draft Project Report and Draft Environmental Document in District

Milestone 100 - Approve Draft Project Report

Milestone 120 - Circulate Draft Environmental Document

Milestone 140 - Conduct Public Hearing

Milestone 160 - Approve final Environmental Document

Milestone 200 - Approve Initiation of PS&E

Milestone 220 - Complete Geometric Base Maps

Milestone 221 - Send Bridge Site Data to Structures Design

Milestone 222 - Initiate Structures Design

Milestone 224 - Send Maps to Right of Way Engineering

Milestone 225 - Initiate Right of Way Appraisals

Milestone 260 - Distribute Skeleton Layouts to Functional Units

Milestone 265 - Send Final Maps to Right of Way

Milestone 275 - Send Structures General Plan to District

Milestone 300 - Circulate Plans for Review

Milestone 360 - Complete Environmental Reevaluation

Milestone 377* - Complete PS&E and send to District Office Engineer

Milestone 378 - Send Structures PS&E to District

Milestone 380 - Send District PS&E to Office of Office Engineer

Milestone 410 - Obtain Right of Way Certification

Milestone 420* - Complete Special Provisions

Milestone 460 - Determine Contract is Ready to List for Advertising

Milestone 480 - Advertise Contract

Milestone 500 - Approve Contract

Milestone 600 - Complete Construction Project

Milestone 700 - Prepare Final Project Files

 

---------------------------------------- O ----------------------------------------

Obtain Right of Way Certification (Milestone 410)

 

---------------------------------------- P ----------------------------------------

Plans, Circulate for Review (Milestone 300)

Prepare Final Project Files (Milestone 700)

Project, Begin Studies (Milestone 000)

Project, Identify Need (Milestone 000)

Project, Prepare Final Files (Milestone 700)

Project Report, Approve Draft (Milestone 100)

Project Report, Circulate Draft in District (Milestone 060)

Project Report, Initiate Draft (Milestone 040)

Project Study Report, Approve (Milestone 010)

PS&E, Approve Initiation of (Milestone 200)

PS&E, Complete and send to District Office Engineer (Milestone 377*)

PS&E, Send District PS&E to Office of Office Engineer (Milestone 380)

PS&E, Send Structures PS&E to District (Milestone 378)

Public Hearing, Conduct (Milestone 140)

PYPSCAN Milestones (See Milestone)

 

---------------------------------------- R ----------------------------------------

Right of Way Appraisals, Initiate (Milestone 225)

Right of Way, Obtain Certification (Milestone 410)

 

---------------------------------------- S ----------------------------------------

Send Bridge Site Data to Structures Design (Milestone 221)

Send District PS&E to Office of Office Engineer (Milestone 380)

Send Final Maps to Right of Way (Milestone 265)

Send Maps to Right of Way Engineering (Milestone 224)

Send Structures General Plan to District (Milestone 275)

Send Structures PS&E to District (Milestone 378)

Skeleton Layouts, Distribute to Functional Units (Milestone 260)

Special Provisions, Complete (Milestone 420*)

Structures Design, Initiate (Milestone 222)

Structures General Plan, Send to District (Milestone 275)

Structures PS&E, Send to District (Milestone 378)

 

* Milestones 377 and 420 are not PYPSCAN Milestones. They were added to reflect the Office Engineer function in the Districts and Headquarters.

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 10, 1997.