PYPSCAN Milestone 420*

Complete Special Provisions

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D428-D429) 

Milestone
Task Group
 
 Last Update

D428
Complete Specifications for Qualified Projects

(420.A)

11/28/94

D429
Review Draft Contract Documents (Nonqualified Project)

(420.A)

11/28/94

* Milestone 420 is not a PYPSCAN Milestone. It was added to reflect the Office Engineer function in the Districts and Headquarters.


TASK D428 (420.A)

Complete Specifications for Qualified Projects

Narrative

For qualified projects, the District Office Engineer prepared the draft contract documents and transmitted the PS&E submittal to the Office of Office Engineer for preparation of final contract documents.

After plans, special provisions, and estimates have been received and the requirements listed in Attachment "A" have been completed, the project is Ready to List for advertising.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D429 (420.A)

Review Draft Contract Documents (Nonqualified Project)

Narrative

For projects that are not qualified, the District Office Engineer compiled the PS&E, circulated the PS&E submittal to district units, and transmitted the submittal to the Office of Office Engineer (OOE) to complete draft contract documents. After completion of the draft contract documents, the district is requested to review them.

After plans, special provisions, and estimate have been reviewed by the district and the requirements in Attachment "A" have been completed, the project is Ready to List for advertising.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 11, 1997.

Go to Top of Document