California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 260

Distribute Skeleton Layouts to Functional Units

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D323-D364) 

Milestone
Task Group
 
 Last Update

D323
Complete Final Right of Way Requirements

(260.A)

11/28/94

D324
Review Contour Grading Plans

(260.B)

11/28/94

D325
Prepare Final Drainage Plan

(260.B)

11/28/94

D326
Send Skeleton Layouts to Traffic Unit

(260.C)

11/28/94

D327
Prepare Traffic Striping, Signing, and Roadside Delineation

(260.C)

11/28/94

D328
Request Traffic Unit to Prepare Lane Closure Charts

(260.C)

11/28/94

D329
Determine Railroad Electrical Requirements

(260.C)

11/28/94

D330
Send Skeleton Layouts to Landscape Unit

(260.C)

11/28/94

D331
Review for Water Well Abandonment

(260.C)

11/28/94

D332
Calculate Final Miscellaneous Quantities

(260.C)

11/28/94

D333
Request Aesthetics Review

(260.C)

11/28/94

D334
Prepare Aesthetics Recommendations

(260.C)

11/28/94

D335
Prepare Final Geometrics

(260.C)

11/28/94

D336
Calculate Final Sanitary Sewer Quantities

(260.D)

11/28/94

D337
Calculate Final Drainage Quantities

(260.D)

11/28/94

D338
Prepare Drainage and Sanitary Sewer Quantity Lists

(260.D)

11/28/94

D339
Calculate Final Earthwork Quantities

(260.D)

11/28/94

D340
Calculate Final Pavement Structural Section Quantities

(260.D)

11/28/94

D341
Send List of Noncommercial Material or Disposal Sites to Environmental Unit

(260.D)

11/28/94

D342
Obtain Approval for Noncommercial Material or Disposal Sites

(260.D)

11/28/94

D343
Prepare Materials Agreement for Noncommercial Material or Disposal Sites

(260.D)

11/28/94

D344
Prepare Unit Price Analysis

(260.D)

11/28/94

D345
Update Estimate in the Basic Engineering Estimating System

(260.D)

11/28/94

D346
Prepare Project Change Request

(260.D)

11/28/94

D347
Request Railroad Funding Participation

(260.E)

11/28/94

D348
Prepare Railroad Participation Cost Estimate

(260.E)

11/28/94

D349
Conduct Hazardous Waste Management Plan Decision Meeting

(260.F)

11/28/94

D350
Obtain Approval for Hazardous Waste Remediation During Project Construction

(260.F)

11/28/94

D351
Prepare PS&E for Hazardous Waste Remediation During Project Construction

(260.F)

11/28/94

D352
Obtain Approval for Hazardous Waste Remediation Prior to Project Construction

(260.F)

11/28/94

D353
Identify Utility Encroachment Exceptions

(260.G)

11/28/94

D354
Obtain Approval for Utility Encroachment Exception

(260.G)

11/28/94

D355
Prepare Plans Identifying High-Risk Utilities

(260.H)

11/28/94

D356
Send Utility Plans to Utilities Unit

(260.H)

11/28/94

D357
Request Utility Relocation Plans from Utility Owners

(260.H)

11/28/94

D358
Send Utility Relocation Plans to Project Development

(260.H)

11/28/94

D359
Update Utility Relocation Cost Estimates

(260.H)

11/28/94

D360
Complete Surveys for Utility Relocations and Other Right of Way

(260.I)

11/28/94

D361
Send Utility Relocation Plans to Office of Structure Design, Landscape, and Traffic Units

(260.J)

11/28/94

D362
Complete In-Place Utility Relocation Plans

(260.J)

11/28/94

D363
Send Utility Relocation Notices to Owners

(260.J)

11/28/94

D364
Complete Utility Relocation Activities

(260.K)

11/28/94

Go to Top of Document


TASK D323 (260.A)

Complete Final Right of Way Requirements

Narrative

The right of way appraisal process, as well as continuing developments in project design, may lead to revisions in right of way requirements. Changes may affect the right of way schedule, so the Right of Way Branch should be notified as soon as changes are identified. The Project Engineer must revise right of way requirements and send appropriate maps to Right of Way Engineering.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D324 (260.B)

Review Contour Grading Plans

Narrative

Contour grading enhances the appearance of earthwork slopes. A preliminary Contour Grading Plan was developed in the early design phase. It may now be necessary to revise the plan to accommodate drainage design and other design details.

Initiator

Sub-Tasks

- Earthwork

- Drainage structures

- Bridges

- Landscaping

- Etc.

Task Duration

References

Go to Top of Document


TASK D325 (260.B)

Prepare Final Drainage Plan

Narrative

Drainage design includes (1) hydrology studies and the development of a preliminary Drainage Report, (2) development of a Drainage Plan, and (3) the preparation of drainage layouts.

The preliminary Drainage Plan should now be finalized.

Initiator

Sub-Tasks

- Drainage areas

- Culvert sizing requirements with hydraulic data (flow lines, head, capacity, etc.)

- Storm drain requirements

- Outfalls

- Flow directional arrows

- Channels

- Etc.

Task Duration

References

Go to Top of Document


TASK D326 (260.C)

Send Skeleton Layouts to Traffic Unit

Narrative

The Traffic Unit previously received geometric base maps and was requested to begin preparation of the Traffic portion of the Plans, Specifications and Estimate (PS&E). Now it is time to send updated data to the Traffic Unit so the Traffic PS&E can be completed.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D327 (260.C)

Prepare Traffic Striping, Signing, and Roadside Delineation

Narrative

Traffic striping, signing, and roadside delineation are included in the Traffic portion of the Plans, Specifications and Estimate. This includes lane lines, pavement markings, and pavement markers. Object markers, delineators, exit and entrance ramp gore striping, crosswalks, limit lines, arrows, and other delineation are also included.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D328 (260.C)

Request Traffic Unit to Prepare Lane Closure Charts

Narrative

Lane closure charts are generally prepared by the Traffic Unit. They identify the number of lanes that can be closed during construction and specify the allowable periods of closure .

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D329 (260.C)

Determine Railroad Electrical Requirements

Narrative

The electrical design portion of the Plans, Specifications and Estimate (PS&E) may include railroad electrical requirements.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D330 (260.C)

Send Skeleton Layouts to Landscape Unit

Narrative

A preliminary Erosion Control Plan was developed as part of the Drainage Plan. The next step is to update the Erosion Control Plan and prepare the landscaping portion of the Plans, Specifications and Estimate (PS&E).

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D331 (260.C)

Review for Water Well Abandonment

Narrative

Sections 13700 and 13806 of the California Water Code deal with the construction and destruction of water wells. Sections 24400 and 24404 of the Health and Safety Code require that abandoned wells be covered, filled, or fenced for safety reasons.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D332 (260.C)

Calculate Final Miscellaneous Quantities

Narrative

Miscellaneous quantities must be calculated for items not covered by the Plans, Specifications and Estimate (PS&E) prepared by functional units. Miscellaneous quantities vary with the project and generally include fences, gates, monuments, water well abandonment, sidewalks, curb and gutters, and guardrail, etc.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D333 (260.C)

Request Aesthetics Review

Narrative

An aesthetics review is conducted to identify aesthetic issues. The review panel may include advisory groups established by local entities, such as architectural review boards, local arts councils, design review committees, and community advisory boards. If local entity groups have not been established, the issues may be discussed with the local entities.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D334 (260.C)

Prepare Aesthetics Recommendations

Narrative

After the aesthetics review is conducted, a summary of recommendations is prepared by the Landscape Unit.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D335 (260.C)

Prepare Final Geometrics

Narrative

Preliminary geometrics were prepared and sent to the functional units for review. Their comments were incorporated into the geometrics, as appropriate. Skeleton layouts were developed for each functional unit for use in preparing their portion of the Plans, Specifications and Estimate. The Project Engineer should add the final roadway features. These geometrics form the basis for final plan sheets.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D336 (260.D)

Calculate Final Sanitary Sewer Quantities

Narrative

Local entities often modify or construct their sanitary sewer facilities prior to construction of Caltrans projects. In these cases, Caltrans is primarily involved in funding considerations. However, if Caltrans designs and constructs the facilities, the contract items of work and quantities must be determined.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D337 (260.D)

Calculate Final Drainage Quantities

Narrative

After the Drainage Plan is completed, contract items are identified and quantities calculated. Drainage items may amount to 25% of all contract items.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D338 (260.D)

Prepare Drainage and Sanitary Sewer Quantity Lists

Narrative

After drainage and sewer quantities have been calculated and entered into the Basic Engineering Estimating System, quantity lists should be prepared. For smaller projects, the drainage and sewer lists may be combined. Separate lists are generally prepared for larger projects.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D339 (260.D)

Calculate Final Earthwork Quantities

Narrative

Preliminary earthwork quantities were calculated after geometric base maps were completed. Final quantities are now calculated. Earthwork includes more than roadway excavation and embankment; it may also include structure excavation, ditch excavation, channel changes, subsidence, unsuitable material, borrow, surplus material, slope rounding, and selected material, etc.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D340 (260.D)

Calculate Final Pavement Structural Section Quantities

Narrative

Pavement structural section quantities were included in project cost estimates since the planning phase. Final structural section quantities should now be calculated.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D341 (260.D)

Send List of Noncommercial Material or Disposal Sites to Environmental Unit

Narrative

Material or disposal sites may be required; for example, if earthwork quantities are not balanced. Commercial sites may be available, but on some projects noncommercial sites will be required. If these sites are not covered in the Final environmental document, it may be necessary to assess potential environmental impacts and prepare the appropriate environmental document.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D342 (260.D)

Obtain Approval for Noncommercial Material or Disposal Sites

Narrative

After the Environmental Unit has reviewed the list of proposed material or disposal sites, a decision can be made to select and approve those sites that satisfy the needs of the project.

Initiator

Sub-Tasks

- Satisfies project needs

- Potential environmental impacts are not significant, and necessary studies and environmental document preparation will not adversely affect project schedule

- Cost effective

- Right of Way Branch purchase site or obtain Materials Agreement

- Environmental Unit obtain Environmental Authorization To Proceed

- Materials Unit assist in development of Materials Agreement

Task Duration

References

Go to Top of Document


TASK D343 (260.D)

Prepare Materials Agreement for Noncommercial Material or Disposal Sites

Narrative

A Materials Agreement is required to formalize conditions of use for noncommercial material or disposal sites. The Right of Way Branch is the lead for this process with the help of the Materials Unit.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D344 (260.D)

Prepare Unit Price Analysis

Narrative

Cost estimates have been continuously prepared and updated since project initiation. To ensure that the final estimates reflect current information, all unit prices must be analyzed prior to completing the final estimates.

Initiator

Sub-Tasks

- Similar projects

- Contractor bids for recent district projects

- Statewide data available from the Office Engineer, including the Contract Items By Item Number Report, annual cost data books, the California Construction Cost Index, plus information from the Basic Engineering Estimating System

- Cost analysis by labor, equipment, and materials

Task Duration

References

Go to Top of Document


TASK D345 (260.D)

Update Estimate in the Basic Engineering Estimating System

Narrative

Estimates have been periodically updated since project initiation. Many final quantities and preliminary unit prices were entered into the Basic Engineering Estimating System (BEES). Now that current unit prices are determined, they should be entered into the BEES.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D346 (260.D)

Prepare Project Change Request

Narrative

The base design estimate must be monitored very closely. When a project estimate exceeds the base estimate, a Project Change Request (PCR) may be required. Project cost is not the only consideration; changes to project schedule or scope may also require a PCR.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D347 (260.E)

Request Railroad Funding Participation

Narrative

An additional step is required for projects with separation structures that eliminate railroad grade crossings. Since railroads may obtain a direct benefit from elimination of a grade crossing, their participation is determined by the Public Utilities Commission (PUC).

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D348 (260.E)

Prepare Railroad Participation Cost Estimate

Narrative

After the Public Utilities Commission (PUC) approves the cost sharing agreement for railroad separation structures, a Railroad Participation Cost Estimate is prepared.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D349 (260.F)

Conduct Hazardous Waste Management Plan Decision Meeting

Narrative

After the Hazardous Waste Management Plan (HWMP) has been developed, a meeting is held to determine whether to remediate prior to or during project construction.

Initiator

Sub-Tasks

NOTE: If hazardous waste remediation is proposed to occur during project construction, Tasks D350 and D351 apply.

If hazardous waste remediation is proposed to occur prior to project construction, Tasks D352 applies.

Task Duration

References

Go to Top of Document


TASK D350 (260.F)

Obtain Approval for Hazardous Waste Remediation During Project Construction

Narrative

Caltrans' policy normally requires remediation to be completed prior to construction. If a decision was made at the Hazardous Waste Management Plan (HWMP) meeting to remediate the hazardous waste during project construction, approval for exception to policy must be obtained from the Deputy Director for Transportation Engineering (DDTE).

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D351 (260.F)

Prepare PS&E for Hazardous Waste Remediation During Project Construction

Narrative

Approval has been granted to perform hazardous waste (HW) remediation during project construction. Now it is necessary to develop the Remedial Action Design (RAD) and PS&E for inclusion in the highway project PS&E.

Initiator

Sub-Tasks

- Statewide HW Remedial Design Contract

- Architectural & Engineering (A&E) Contract

- Caltrans' staff (requires close coordination with HW Units in the district and HQ)

Task Duration

References

Go to Top of Document


TASK D352 (260.F)

Obtain Approval for Hazardous Waste Remediation Prior to Project Construction

Narrative

A decision was made at the Hazardous Waste Management Plan (HWMP) Meeting to remediate the hazardous waste (HW) problem prior to project construction. This requires a Remedial Action Design (RAD) and PS&E.

Initiator

Sub-Tasks

- Statewide HW Remedial Design Contract

- Architectural & Engineering (A&E) Contract

- Caltrans' staff (requires close coordination with HW Units in the district and HQ)

Task Duration

References

Go to Top of Document


TASK D353 (260.G)

Identify Utility Encroachment Exceptions

Narrative

Caltrans' policy states that all utility facilities must be located outside the freeway or expressway right of way. Exceptions to this policy require OPPD approval.

Initiator

Sub-Tasks

- Right of Way Branch

- Maintenance Unit

- Project Development Coordinator

Task Duration

References

Go to Top of Document


TASK D354 (260.G)

Obtain Approval for Utility Encroachment Exception

Narrative

The need for an exception to Caltrans' utility encroachment policy has been determined. Now the request for exception must be processed through OPPD.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D355 (260.H)

Prepare Plans Identifying High-Risk Utilities

Narrative

An important phase of relocating utilities is the identification of high-risk utilities. Types of facilities classified as high or low risk are identified in the "Policy on High and Low Risk Underground Facilities Within Highway Rights of Way".

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D356 (260.H)

Send Utility Plans to Utilities Unit

Narrative

After skeleton layouts (preliminary Utility Plans) have been updated with information provided by the utility owners, the Project Engineer must indicate which facilities need to be removed, elocated, or adjusted.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D357 (260.H)

Request Utility Relocation Plans from Utility Owners

Narrative

After receiving plans from the Project Engineer, the Utilities Unit should request the utility owners to prepare relocation plans for conflicting utilities.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D358 (260.H)

Send Utility Relocation Plans to Project Development

Narrative

Before relocation of utilities begins, the Utilities Unit should request the Project Development Unit (PDU) to perform a final check of the utility relocation plans to ensure that the relocation plans are compatible with the construction plans.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D359 (260.H)

Update Utility Relocation Cost Estimates

Narrative

After the utility relocation plans have been prepared, the utility cost estimate should be updated.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D360 (260.I)

Complete Surveys for Utility Relocations and Other Right of Way

Narrative

Survey activities have been required throughout the design process. Specific data for structures, drainage, etc. were previously obtained. During the development of utility relocation plans, surveys were required to locate certain utilities, and positive location was required for all utilities. Required surveys should now be finished so that utility relocation plans and project design may be completed.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D361 (260.J)

Send Utility Relocation Plans to Office of Structure Design, Landscape, and Traffic Units

Narrative

The approved utility relocation plans are sent to Office of Structure Design (OSD), Landscape, and Traffic Units to finalize their portion of the PS&E. The relocation plans will identify the location of utilities and service points.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D362 (260.J)

Complete In-Place Utility Relocation Plans

Narrative

After resolving the concerns of affected units, the Contract Utility Plans may be completed. Utilities to be relocated are shown in their proposed locations. Design changes should be reported to the Utilities Unit.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D363 (260.J)

Send Utility Relocation Notices to Owners

Narrative

The Utility Relocation Notices are mandatory legal documents that notify utility owners what must be done, when it is to be done, and who is financially and contractually responsible.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D364 (260.K)

Complete Utility Relocation Activities

Narrative

Utility Relocation Notices have been sent to utility owners. This initiated the process for relocation, removal, readjustment, or abandonment of utilities that will interfere with project construction. The utility relocation work must be inspected for compliance with the relocation plans. The Utility Unit is responsible for this activity with assistance from the Construction Unit.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 12, 1997.

Go to Top of Document