California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 100

Approve Draft Project Report

(Click on highlighted Task to see detailed information.)

 Planning
Task
Number

Planning Tasks (P161-P172) 

Milestone
Task Group
 
 Last Update

P161
Obtain Master Distribution and Invitation Lists

(100.A)

11/28/94

P162
Identify Public Comment Period, Date and Location of Public Hearing

(100.A)

11/28/94

P163
Prepare Notices Regarding Public Hearing and Availability of Draft Environmental Document

(100.A)

11/28/94

P164
Obtain FHWA Approval to Circulate Draft Environmental Document

(100.A)

11/28/94

P165
Prepare Draft Environmental Document for Circulation

(100.A)

11/28/94

P166
Execute Cooperative Agreement with Local Entities for PS&E

(100.B)

11/28/94

P167
Review Need for Consultant Services for PS&E

(100.B)

11/28/94

P168
Initiate Contracting-Out Process for Consultant Services for PS&E

(100.B)

11/28/94

P169
Advertise for Consultant Services for PS&E

(100.B)

11/28/94

P170
Select Consultant for PS&E

(100.B)

11/28/94

P171
Negotiate Consultant Contract for PS&E

(100.B)

11/28/94

P172
Execute Consultant Contract for PS&E

(100.B)

11/28/94

Go to Top of Document


TASK P161 (100.A)

Obtain Master Distribution and Invitation Lists

Narrative

Public hearings may be held for projects that have significant social, economic, or environmental impacts. The hearings are held to inform the public of the project and to obtain formal public input. The first step is to obtain a master distribution and invitation list for those groups, individuals, and entities who may have an interest in the project.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P162 (100.A)

Identify Public Comment Period, Date and Location of Public Hearing

Narrative

Public comment periods for State and federal documents differ, so it is necessary to determine the applicable controlling schedule.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P163 (100.A)

Prepare Notices Regarding Public Hearing and Availability of Draft Environmental Document

Narrative

A public hearing may be held for projects with significant social, economic, or environmental impacts. Projects with lesser impacts tend to be noncontroversial and the public or a local entity are not likely to request a public hearing; for these projects it is usually adequate to provide the public with the opportunity for a hearing. In either case, the public must be notified of the availability of the Draft environmental document.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P164 (100.A)

Obtain FHWA Approval to Circulate Draft Environmental Document

Narrative

The FHWA may have reviewed the Draft environmental document during development of the Draft Project Report. However, FHWA approval is required to circulate the Draft environmental document.

Initiator

Sub-Tasks

- Cover Sheet signed by District Director

- Five copies of the Draft Negative Declaration or six copies of the Draft Environmental Impact Report

- Two copies of backup reports

Task Duration

References

Go to Top of Document


TASK P165 (100.A)

Prepare Draft Environmental Document for Circulation

Narrative

After the Draft environmental document has been completed and the District Director and FHWA (if required) approval to circulate have been obtained, the document is prepared for circulation.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P166 (100.B)

Execute Cooperative Agreement with Local Entities for PS&E

Narrative

The approved Draft Project Report authorizes Cooperative Agreements with local entities and specifically identifies items to be covered by such agreements; such as responsibility for cost and preparation of the PS&E. Following approval of the draft agreement by OPPD (or by use of preapproved forms), the Cooperative Agreement is executed by the local entity and the District Director.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P167 (100.B)

Review Need for Consultant Services for PS&E

Narrative

The process of contracting for consultant services requires the participation of involved Caltrans' functional units and, when appropriate, the Department of General Services. After the Draft Project Report has been approved, a decision must be made whether to develop the PS&E by contract or with Caltrans' staff.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P168 (100.B)

Initiate Contracting-Out Process for Consultant Services for PS&E

Narrative

After the decision has been made to contract out the preparation of the PS&E, it is important to initiate the process as soon as possible to avoid potential delays.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P169 (100.B)

Advertise for Consultant Services for PS&E

Narrative

Caltrans has standardized procedures for advertisement, to ensure a wide distribution to qualified firms and to ensure compliance with applicable laws. In almost all cases, the advertising process is handled by the HQ Consultant Services Branch, in cooperation with the HQ Contracts Service Office.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P170 (100.B)

Select Consultant for PS&E

Narrative

The Consultant Selection Committee evaluates the consultants' qualifications in order to select the best-qualified firm.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P171 (100.B)

Negotiate Consultant Contract for PS&E

Narrative

Negotiations with the highest-ranked consultant firm begin after the selection process is completed. The objective of negotiations is to obtain consultant services at a cost that is fair and reasonable to both the state and to the consultant. Negotiations are confidential; only those with a need to know should have access to the consultant's cost proposal and the Caltrans estimate.

Initiator

Sub-Tasks

At the same time, the Negotiations Board evaluates the consultant's cost proposal in comparison with the Caltrans estimate.

Task Duration

References

Go to Top of Document


TASK P172 (100.B)

Execute Consultant Contract for PS&E

Narrative

After negotiations are complete, the consultant contract is completed and executed. This requires review and approval by the district, HQ Contracts Service Office, Legal Division, and if required - the Department of General Services. The contract is not fully executed until required approvals have been obtained. The consultant may not commence work until it has been fully executed and Caltrans authorizes the consultant to proceed.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 11, 1997.

Go to Top of Document