California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 060

Circulate Draft Project Report and Draft Environmental Document in District

(Click on highlighted Task to see detailed information.)

 Planning
Task
Number

Planning Tasks (P156-P160) 

Milestone
Task Group
 
 Last Update

P156
Circulate Draft Project Report for Review

(060.A)

11/28/94

P157
Complete Draft Environmental Document

(060.A)

11/28/94

P158
Complete Draft Project Report

(060.A)

11/28/94

P159
Review Need for Public Hearing Process

(060.A)

11/28/94

P160
Approve Draft Project Report

(060.A)

11/28/94


TASK P156 (060.A)

Circulate Draft Project Report for Review

Narrative

The Draft Project Report, which includes the Draft environmental document, is circulated to appropriate district units for review.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P157 (060.A)

Complete Draft Environmental Document

Narrative

The Draft environmental document should be revised to reflect the comments received from the review by district units (and HQ, if applicable).

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P158 (060.A)

Complete Draft Project Report

Narrative

Concurrent with the revision of the Draft environmental document the Draft Project Report should be completed. Comments returned from district units are considered for incorporation into the Draft Project Report, if appropriate.

If project is Categorically Exempt, the Project Report is now prepared in final form.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P159 (060.A)

Review Need for Public Hearing Process

Narrative

Public hearings provide a forum for discussing project need, alternative locations, alternative design features, and potential social, economic, and environmental effects. The public hearing process applies to projects with the following potential effects: (1) require a significant amount of right of way, (2) substantially change the layout or function of connecting roadways or of the facility being improved, (3) have a significant adverse impact on abutting real property, and (4) have significant social, economic, environmental, or other effects.

The purpose of the public hearing process is to obtain public input and acceptance ensuring that subsequent project decisions are consistent with federal, State, and local objectives.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK P160 (060.A)

Approve Draft Project Report

Narrative

The Draft Project Report (including the Draft environmental document) is submitted to the District Director to approve a recommendation to proceed with the public hearing process.

If the project is Categorically Exempt, approval authorizes the project to proceed to the design phase.

If there is no federal involvement, but the project requires an environmental document, approval of the Draft Project Report authorizes circulation of the Draft Environmental Impact Report and proceeding with the public hearing process.

If the project requires an environmental document, and there is federal involvement, approval of the Draft Project Report provides authorization to proceed with the public hearing process.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 11, 1997.

Go to Top of Document